The following
deliverable:
|
Deliverable name: |
Periodic Progress Report: Month 15 |
||
|
Deliverable number: |
D 7.2 |
||
|
is
now complete. |
*
It is available for your inspection
A copy can be sent to you on request.
Relevant descriptive documents are attached.
2 bound, 1 unbound copies herewith (public deliverables).
2 copies herewith (other deliverables). |
Tick all that apply |
|
|
The deliverable is: |
X on paper on WWW |
|
|
|||
|
an event software X other |
Report attached below. |
(tick
one) |
|
|||
For
all paper deliverables, and other deliverables as appropriate:
|
Date: |
15 September, 2003 |
Version: |
1 |
|
Author: |
Iorizzo and Rydberg-Cox |
No. of pages: |
This cover plus 12 pages |
|
Status: |
Public Restricted *Internal (tick one) |
||
|
Commission
use only Keywords: |
|||
|
Description: |
|||
|
Comments:
|
|||
PROJECT PROGRESS REPORT
Project: CHLT-IST-2001-32745
Progress Report Number: 7
Period: 1
June - 31 August 2003
Author: Dolores
Iorizzo
Organisation Imperial
College London
Address: Centre for
the History of Science, Technology and Medicine
Sherfield
Building - Room 445,
Exhibition
Road, London SW7 2AZ
Email: d.iorizzo@ic.ac.uk Phone: + 44 207-594-9355
1. Work planned during
this period........................................................................................ 3
2. Achievements of WP 1
:Advanced Digital Library Applications....................................... 4
3. Achievements of WP 2 :
Computational Linguistics.......................................................... 4
4. Achievements of WP 3 :
Collaborative Infrastructure........................................................ 5
5. Achievements of WP 4 :
Old Norse Morphological Analyzer........................................... 5
6. Achievements of WP 5 :
Neo-Latin Morphological Analyzer........................................... 5
7. Achievements of WP 6 :
Early Modern Latin Corpus....................................................... 5
8. Achievements of WP 7 :
Management of Consortium....................................................... 6
9. Achievements of WP 8:
Integration.................................................................................... 6
10. Achievements
of Workpackage 9: Dissemination and exploitation................................ 7
11. Technical
options adopted.............................................................................................. 7
12. Meetings
held.................................................................................................................. 7
13. Assessment
of interim results......................................................................................... 7
13.1. Objectives set versus
objective attained, deviations................................................... 7
13.2. Issues.......................................................................................................................... 8
14. Check list
of deliverables completed............................................................................... 9
15. Resources
use for the first period................................................................................. 11
16. Work
planned next reporting period............................................................................. 12
17. Others........................................................................................................................... 12
18. Names or
address change, responsibility reassignment or other................................... 13
CHLT has been active for just over a year and this report outlines the work of months 13 Ð 15 in the second year of the project. At the first annual review meeting CHLT was given permission to move to a quarterly reporting system (instead of a bi-monthly one) in light of the striking imbalance of reporting requirement between the US and EC partners. Work in this period has concentrated on three phases: Phase 2: Tools Development was initiated in month 6 and has continued on schedule, as has Phase 3: Evaluation which began in month 10. Phase 4: Integration has been active from the start of the project. Progress has been made in the following areas:
á Document Cluster Visualization Tool
á Word Profile Tool
á Facilities to Accept and Preserve Feedback
á Integration of Text Processing System
á Old Norse Morphological Analyzer
á Latin Morphological Analyzer
á Early Modern Latin Texts
á CHLT Website Development
á Project and Programming Integration
á Integration Meetings
á Dissemination
The following Workpackages were active during the period :
WP1 Ð Advanced Digital Library Applications
WP2 Ð Computational Linguistics
WP3 Ð Collaborative Infrastructure
WP4 Ð Old Norse Morphological Analyzer
WP5 Ð Neo-Latin Morphological Analyzer
WP6 Ð Test-bed Development
WP7 Ð Management of Consortium
WP8 Ð Integration
WP9 Ð Dissemination and Exploitation
WP Leader : Stefan Reuger
Scheduled dates
: 1 June Ð 31 August, 2003
Actual dates: September 2003
Deliverables: No deliverables due this period.
á Concentration of effort on developing the design of interface for the Cluster and Visualization Tool. On schedule for delivery at the end of January 2004.
Estimated achievement: 42 % as planned
WP Leader : Jeff Rydberg-Cox
Scheduled dates
: 1 June Ð 31 August, 2003
Actual dates: September 2003
Deliverables: No
deliverables due this period.